Which phase follows the risk assessment in the System Development Life Cycle (SDLC)?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the Certified Administrative Professional Exam with comprehensive quizzes. Sharpen your skills with multiple choice questions, each with detailed explanations. Achieve success on your CAP exam!

In the System Development Life Cycle (SDLC), the phase that follows risk assessment is typically the Development/Acquirement phase. During this phase, the decisions made in the planning and risk assessment stages are put into action. This includes designing the system, developing the necessary software, or acquiring the required components and infrastructure.

The Development/Acquirement phase is essential as it transforms the identified requirements and addressed risks from earlier assessments into tangible solutions. This phase is focused on building the system or procuring the necessary tools and resources that were determined as suitable during the previous stages.

While the planning phase is crucial for laying out the overall strategy and goals, it occurs before the risk assessment. The implementation phase comes after development, focusing on putting the finished product into an operational environment. Similarly, the maintenance phase is the final stage of the SDLC that deals with the ongoing support and updates for the system after it has been deployed. Therefore, following risk assessment, Development/Acquirement is the logical progression in creating a robust system.